How many scheduled hours are there for a 60-day project consisting of 8-hour days?

Prepare for the Virginia Class A Contractor License Exam. Study using flashcards and multiple choice questions, each question equipped with hints and explanations. Ace your exam!

Multiple Choice

How many scheduled hours are there for a 60-day project consisting of 8-hour days?

Explanation:
Total scheduled hours come from multiplying the number of days by the number of hours worked each day. For a 60-day project with 8-hour days, you multiply 60 by 8 to get 480 hours. This assumes every scheduled day is a full 8-hour workday and there are no holidays or overtime affecting the plan. The other numbers would require more hours per day or additional days beyond the given 8 hours per day.

Total scheduled hours come from multiplying the number of days by the number of hours worked each day. For a 60-day project with 8-hour days, you multiply 60 by 8 to get 480 hours. This assumes every scheduled day is a full 8-hour workday and there are no holidays or overtime affecting the plan. The other numbers would require more hours per day or additional days beyond the given 8 hours per day.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy